Phase 1 (2027)

Key Deployments

Key Deployments

IRIS 3 – 50 MW – Q1 2027

This phase focuses on rapid deployment, early revenue generation, and foundational campus infrastructure.

Phase 2 (2028-2029)

Key Deployments

Key Deployments

Establishes the next operational AI and cloud infrastructure facilities across the campus, delivering approximately 126 MW of additional IT capacity.

IRIS 1 – 75 MW – Q2 2028

200 MW GIS Substation – Q2 2028

IRIS 4 – 54 MW – Q3 2029

IRIS 5 – 72 MW – Q3 2029

Phase 3 (2030-2031)

Key Deployments

Key Deployments

IRIS 6 & 7 – 108 MW – Q2 2030

IRIS 8 & 11 – 108 MW – Q4 2030

IRIS 9 & 10 – 108 MW – Q4 2030

500 MW GIS Substation – Q2 2030

IRIS 2 – 135 MW – Q4 2031