IRIS Europe’s Next Hyperscale AI Data Center Campus

IRIS is a 710 MW hyperscale data center campus strategically located in Central Europe — purpose-built for AI, cloud, and high-density compute environments.

Watch Campus Overview

Hero image

710

710

MWe

Total Campus Power

440

440

MWit

Deployable IT Capacity

110

110

MWe

MWe

Phase 1 Third-Party PV Solar Integration

15

15

MWe

MWe

Phase 1 Third-Party BESS Energy Storage

Icon

Interactive Masterplan

Icon

Interactive Masterplan

A campus built at hyperscale

Icon

Interactive Masterplan

A campus built at hyperscale

11 Planned Facilities

11 FACILITIES. 710 MW POWER. LIMITLESS POTENTIAL.

The IRIS Data Center Campus is a 710 MW multi-phase hyperscale development in Most, Czechia — strategically located 20 km from the German border. Spanning East and West campus divisions across 11 facilities, it delivers 440 MW of total IT load for AI, HPC, and cloud workloads. Phase 1 launches in 2027 with IRIS 1–5, followed by West Campus expansion through IRIS 6–11 in Phase 2.

IRIS 1

Strategic AI Facility

IRIS 2

Flagship AI Compute Facility

IRIS 3 (HPC)

High Density AI Clusters

IRIS 4-11

Modular Hyperscale Expansion Campus

11 Planned Facilities

11 FACILITIES. 710 MW POWER. LIMITLESS POTENTIAL.

The IRIS Data Center Campus is a 710 MW multi-phase hyperscale development in Most, Czechia — strategically located 20 km from the German border. Spanning East and West campus divisions across 11 facilities, it delivers 440 MW of total IT load for AI, HPC, and cloud workloads. Phase 1 launches in 2027 with IRIS 1–5, followed by West Campus expansion through IRIS 6–11 in Phase 2.

IRIS 1

Strategic AI Facility

IRIS 2

Flagship AI Compute Facility

IRIS 3 (HPC)

High Density AI Clusters

IRIS 4-11

Modular Hyperscale Expansion Campus

Interactive Masterplan
Map
Icon

Strategically Positioned

Built for Europe.
Designed for the Future.

Located in Most, Czechia — just 20 km from Germany — IRIS is strategically positioned to power Central & Eastern Europe’s AI revolution with committed power, low latency connectivity and sustainable infrastructure.

Proximity To Major Markets

20 km from Germany
85 km from Prague

Low Latency Connectivity

<5ms to Frankfurt
via multiple fiber routes

Future Ready Infrastructure

Scalable, sustainable
and AI-optimized

Icon

AI-Ready Infrastructure

Purpose-Built For AI Workloads

A campus built at hyperscale

High Density AI Compute

Designed for GPU clusters and AI training

High Density AI Compute

Designed for GPU clusters and AI training

Direct Liquid Cooling (DLC)

Advanced cooling for maximum performance

HPC Ready

Built for high performance computing at scale

HPC Ready

Built for high performance computing at scale

Hyperscale Architecture

Scalable, resilient and future-proof design

Hyperscale Architecture

Scalable, resilient and future-proof design

Icon

Sustainability By Design

Powering A Greener Future

A campus built at hyperscale

Renewable Energy Integration

Phase 1 Third-Party 110 MW solar + 15 MW battery storage

Heat Recovery Solutions

Waste heat reused through district heating infrastructure

Heat Recovery Solutions

Waste heat reused through district heating infrastructure

Low-Carbon Energy Strategy

Future compatibility with nuclear and other low-carbon energy sources

Icon

Phased Development Roadmap

From Vision To Reality

A campus built at hyperscale

2027-2029

Phase 1

Initial Deployment

IRIS 3 – 50 MW – Q1 2027

IRIS 1 – 75 MW – Q2 2028

200 MW GIS Substation – Q2 2028

IRIS 4 – 54 MW – Q3 2029

IRIS 5 – 72 MW – Q3 2029

2030–2031

Phase 2

Campus Expansion

IRIS 6 & 7 – Q2 2030

IRIS 8 & 11 – Q4 2030

IRIS 9 & 10 – Q4 2030

500 MW GIS Substation – Q2 2030

IRIS 2 – 135 MW – Q4 2031

Let’s Build The Future Of AI Together

Join us in building Europe’s most advanced AI and cloud infrastructure campus.

CTA Image